Metro West tunnel nears completion in major Sydney upgrade

10 News First · Just In
10 News First
10 News First
Just In

Sydney’s Metro West tunnel is now 97% complete, with just 700 metres left to dig beneath Darling Harbour. The $25 billion line will link Westmead to the CBD via Parramatta, with track laying, station builds and testing to follow.

Breakdown
  • Tunnel boring for Metro West is 97% complete, with 700 metres left to finish. 11s
  • The project will connect Westmead to the city, linking Parramatta CBD and Sydney CBD. 21s
  • After tunnelling, the next steps are track laying, station construction, and extensive testing. 41s
  • Metro West is scheduled to begin operations in 2032. 57s
  • At $25 billion, Metro West is Australia's largest public transport project. 1m 3s